Project : Substation Works
Client : Tenaga Nasional Berhad
Year : 2013 - 2018
Works involved:
Installing equipment e.g. transformers, switchgears, VCB, feeder pillars and termination works
Compact sub installation
Preventive maintenance
Breakdown services
EFI installation






Project : Streetlight Rectification Works for Zone A, B, C, D, E and F in MEDINI
Client : Medini Iskandar Malaysia Sdn Bhd
Year : 2020 - 2021
Works involved:
Phase balancing
Replacement of faulty cable and streetlight components
Make good of everything for handover to Majlis Perbandaran Iskandar Puteri






Project : Various Electrical Works
Client : UTM Skudai



Wiring Installation



Relay Calibration



VCB Servicing



Feeder Pillar Dismantling and Installation



Dismantling of Old Transformer and Installation of 2.5MVA Transformer
Cable Fault Location and Rectification






Lightning Arrestor Installation at Dewan Sultan Iskandar



Alarm System Installation